Loan/Grant/Credit number |
IDA-6767- KH |
||
Project Name |
Road Connectivity Improvement Project (RCIP) |
||
Sector/Sub-Sector |
Infrastructure (Improvement and Maintenance of Rural Roads) |
||
Executing Agency (EA) |
Ministry of Economic and Finance (MEF) |
||
Implementing Agency (IA) |
Ministry of Rural Development (MRD) |
||
Total Project Cost (US$ million) |
USD 50 Million |
||
Financing Source(s) |
Financiers |
Amount (US$ million) |
Share of Total |
World Bank, IDA |
USD 50 Million |
100% |
|
Date of Loan/Grant Approval |
16 July 2020 |
||
Date of Signing of Loan/Grant Agreements |
05 August 2020 |
||
Date of Loan/Grant Effectiveness |
26 October 2020 |
||
Closing Date of Loan/Grant |
31 July 2027 |
||
Revised closing date (if applicable) |
N/A |
||
Dates of Last Review Mission (if applicable) |
18/ October/2023 to 26/ October 2023 |
||
Project Impact |
The project impact is to improve climate-resilient road access to key facilities for economic growth and human capital development in targeted provinces. |
||
Project Outcome |
The expected outcomes will enhance the access of people from the project area spend less time to reach the closest economic and development facilities. |
||
Project Component |
Component 1 –
National & Provincial Road Improvement (MPWT)
Component 2 – Rural Roads Improvement (MRD) USD 47 Millions Component 3 – Institutional Development and Project Management USD 3 Million Component 4 - Contingent Emergency Response |
||
Allocation of Loan Proceeds (Component 2) |
Components |
||
Sub-Component 2.1 – Improvement and Maintenance of targeted rural roads |
|||
Sub-Component 2.2 –Supervision and Design |
|||
Project Area |
Kratie, Kampong Cham, and Tbong Khmum Province |
||
Overall Project Progress (as of this report) |
Actual: 41.50% |
||
Elapsed time |
Elapsed time:
35months from the Loan effectiveness date By Packages: |
0 Comments